c. the Multidisciplinary Working Group Implementation of Moiwana
Judgment, in charge of the integral implementation of the Judgment;
d. the Stichting Fonds Ontwikkeling Moiwana Gemeenschap (The
Foundation Fund Development for Moiwana Community), a private
foundation that is charged with the development of the village, for which
the State has reserved an amount of US $1,200,000 that will be
available on the basis of reimbursement per project. The Board of the
Foundation has been established with one representative of the Moiwana
surviving relatives, one representative of the State and a joint
representative. The Foundation was registered on April 4, 2006;
e. the National Commission on Land Rights (NCLR), responsible for an
integral approach to the land rights issue in Suriname and for the
implementation of the aspect of the Judgment concerning the land rights
issue in Moiwana; and
f. a Coordination Team, in charge of preparing the investigation and
judicial process of several specific punishable acts, among them those
perpetrated in Moiwana in 1986.
the expenses incurred to implement the necessary measures to comply with the
Judgement fall on the State and involve the Ministry of Finance, the Ministry of
Foreign Affairs, the Ministry of Regional Development, and the Ministry of
Justice and Police;
reparations for material and moral damages have been prepared and
“expectations are that the payment will be made at the latest on the 14th of July
for the people that have been identified by the institutions involved.” The data
of fifteen surviving relatives are not yet completed and nine have died in the
meantime;
with regard to the compensation for costs, the State will proceed to the
payment of US $27,000 to Stichting Moiwana and of US $10,000 to Forest
Peoples Programme “at the latest on the 14th of July.” With regard to the
payment to Association Moiwana (US $8,000), the State affirms that “the
payments will only be made on the basis of reimbursement of expenses. As per
[that] day, the 14th of July 2006, no statement of expenses [has been]
submitted to the Working Group”;
the monument in memory of the victims will be built in a 60-day working period
starting in August 2006, after the rainy season.
The Working Group is
implementing this project in close cooperation with the Directorate of Culture.
On the 5th of July 2006, the Council of Ministers approved the design – a
“further elaboration of a design made by Moiwana youth” – as well as the
accompanying budget to cover the approximate costs of US $160,000. An
agreement was reached about the location and soon an agreement was to be
signed with the artist. On July 15, 2006, during a ceremony for public apology,
a model of this project was to be shown;
preparations for a ceremony of public apology have been made and the
ceremony is to take place on July 15, 2006. The “preparations […] were made
in close consultation with the representatives of the surviving relatives” and “in
accordance with the Auka culture the public apology will be accompanied by
rituals and ceremonies”; and
regarding the recovery of the remains of the victims for delivery to the
surviving community, “the data mentioned in the Judgement cannot be
completely confirmed by the persons involved.” Consultations to relevant
entities and persons are being conducted, however “[t]he information must be
qualified as: fragmented and contradictory. To fill these gaps the Working
Group is collecting additional data.”